Rincon Long Duration Energy Storage Solar Microgrid

Demonstrates a long-duration flow battery within a commercial microgrid

Rincon Band of Luiseño Indians

Recipient

Valley Center, CA

Recipient Location

40th

Senate District

75th

Assembly District

beenhere

$158,668

Amount Spent

refresh

Active

Project Status

Project Update

The microgrid design is 90 percent complete. The SDG&E interconnection application was submitted, and the utility completed its supplemental review. Third-party financing has been secured. Processes to secure a right-of-way easement and temporary access permit are in progress. The long-duration energy storage system has been manufactured and awaits shipment to the project site. Other procurement and site mobilization activities are proceeding.

The Issue

Non-lithium energy storage technologies have faced several barriers to adoption by California utility customers. Flow batteries have suffered from limitations affecting scale, efficiency, cost, and ability to quickly ramp up to support customers in an outage. As a result, customers and financiers have not considered flow batteries to be sufficiently mature for widespread adoption.

Project Innovation

This project will demonstrate a vanadium redox flow battery system to provide 400kW of load for at least 10 hours. The energy storage system will be interconnected with solar PV to create a microgrid that will provide resiliency and cost savings for a commercial building, which is also used as an emergency public shelter.

Project Goals

Deploy and demonstrate a flow battery that can provide 10 hours of energy at 400 kW with grid-forming functionality.

Project Benefits

By demonstrating the integration of vanadium redox flow batteries as a long-duration energy storage system in a commercial microgrid, the project will support the understanding of how the performance characteristics of flow batteries can support a microgrid. Commercializing flow batteries as long-duration energy storage systems will enable the technology to contribute to meeting California's clean energy goals for resiliency, sustainability, cost savings, and safety.

Lower Costs

Affordability

The project will provide onsite distributed renewable energy resources and energy storage capacity for load shifting to reduce customer electricity costs over the project’s 25-year lifetime.

Energy Security

Energy Security

The project will increase tribal energy security and self-reliance by providing onsite renewable generation and energy storage resource that displace consumption of imported electricity and standby diesel generation fuel. The project will also protect customer loads from public safety power shutoffs and other long-duration outage events.

Environmental & Public Health

Environmental Sustainability

Microgrid with solar generation and long-duration energy storage will reduce the Rincon community’s greenhouse gas footprint and reduce local criteria pollutants attributable to diesel combustion of backup generators.

Key Project Members

Project Member

Josh Simmons

President, Lead Project Manager and Lead Technical Consultant
Prosper Sustainably, LLC
Project Member

Robert Clark

Tribal Administrator
Rincon Band of Luiseno Indians
Project Member

Ben Peters

Sr. Project Developer
PowerFlex
Project Member

Michael Burr

Principal
Microgrid Initiatives
Project Member

Dustin Jolley

Principal
OurEnergy, LLC
Project Member

Colin Boone

Vice President, Sales
Invinity Energy Systems

Subrecipients

Rocket

Prosper Sustainably, LLC

Rocket

OurEnergy LLC

Rocket

Match Partners

Rocket

Rincon Band of Luiseño Indians

Rocket

Contact the Team

*Required